ERCOT’s Batch Zero Process On Hold Due To Data Center Audit
by Samantha N. Miller
As previously reported, the Public Utility Commission of Texas (PUC) on June 18, 2026 approved Electric Reliability Council of Texas (ERCOT) Batch Zero revision requests – PGRR145 Batch Zero Process for Large Load Interconnections and NPRR1325 Related to PGRR145, Batch Zero Process for Large Load Interconnections. The new batch framework groups large projects of 75 megawatts and greater into a single interconnection study, which will allow ERCOT to better determine how much power the system can handle and identify needed transmission upgrades. ERCOT previously assessed large loads on an individual basis, but this prior process triggered restudies of large load requests due to offsetting impacts from nearby loads also seeking interconnections. Batch Zero was designed to reduce these study inefficiencies, which is increasingly important given the growing volume of large load interconnection requests in Texas.
Although ERCOT anticipated notifying Batch Zero applicants of their project classification this August, Governor Greg Abbott’s August 3rd directive requiring a complete verification and audit of all data centers advancing through ERCOT’s interconnection process has forced ERCOT to shift course. In his directive, Governor Abbot asked that the audit be completed before any additional data centers are approved to move forward. ERCOT thus filed requests for good cause exceptions, which were granted on August 20, 2026, to temporarily pause the Batch Zero interconnection process. Reports indicate that the audit will take several months, so ERCOT was unable to meet the September 2nd deadline to begin the Batch Zero study itself.
During the pause, ERCOT will verify the accuracy of information large load developers submitted in support of their interconnection requests. ERCOT recently issued Requests for Information (RFIs) pursuant to Governor Abbott’s letter and signaled that it may issue more RFIs once it is able to analyze the information. ERCOT plans to confirm which projects qualify for Batch Zero inclusion and release a report on the broader grid impacts of data centers on December 10, 2026.
It is unclear yet what impact the delay on Batch Zero will have on transmission planning and other ERCOT-driven studies which require results from the interconnection study. And even though Batch Zero has been paused, ERCOT and stakeholders are beginning to develop a framework for Batch 1+, the next phase of the data center integration process. Depending on the outcome of the audit and delay in Batch Zero, future batch applications are expected to open in Summer 2027.
Samantha Miller is an Associate in the Firm’s Energy and Utility Practice Group. If you would like additional information or have questions related to this article or other matters, please contact Samantha at 512.322.5808 or smiller@lglawfirm.com.